News

This page will contain a summary of the main activities being undertaken by the project team

July 2016

  • updated hydraulic model of the River Carron, River Avon, Grange Burn and Forth Estuary completed
  • option appraisal stage of the project commenced

June 2016

  • topographic surveys completed
  • initial environmental surveys completed

January to June 2016

  • topographic survey field works ongoing
  • environmental surveys ongoing
  • hydrology and coastal model boundaries updated
  • preparations for ground investigations ongoing
  • development of communications plan
  • development of consenting strategy
  • gathering utility (pipes and cables) information